Merriweather Crescent Parking Structure

Columbia, MD
ARCHITECT:
Fox Architects
CONTRACTOR:
The Whiting-Turner Contracting Company
Metromont Project Details

Project Overview

Known as Merriweather Crescent MWD-30A, the nine-level, 426,996-SF structure is four bays wide and is comprised of 1,307 pieces of precast manufactured at Metromont’s Shockey Precast plant in Winchester, VA. Three architectural concrete mixes were used to achieve the exterior finishes.

The project featured some unusual design components and our Engineering team was brought on early in the project to help finalize the contract drawings using our layouts and coordination information. The Northeast corner of the parking garage was designed to house an EMT squad and includes fire truck parking in the sub-level, under the precast products. Because of this, we engineered the Northeast corner of the precast structure with expansion joints and a shear wall so it could function as a completely stand-alone building. This was designed to allow the EMT “building” to remain standing in the event of a structural catastrophic event. Weekly engineering conference calls facilitated the design process and the EOR and Architect were open to our work and suggestions during the design of this complicated structure. The Engineering team combined columns to the end of the walls as Pilasters to reduce the number of precast pieces, which saved on shipping and precast erection costs. They also lengthened the double tee flanges into the opening between the vertical ramp walls, eliminating the need for fencing or cabling in some areas. As originally envisioned, the exterior was to have a separate overlaid architectural façade to give a “picture framed” look. The budget couldn’t accommodate this feature, so panels were cast in two colors and the picture frame protruded 2” proud of the framed spandrels.

The use of precast enabled construction to progress at a speed that met the general contractor and the owner’s schedule. Shockey Precast used two cranes, starting one week apart, to simultaneously erect the precast. With a tight construction site and limited storage, space wasn’t available to accommodate the number of trailers delivering precast. The Project Team quickly realized this scenario could potentially delay delivery and erection of the precast, so the owner and general contractor worked with Shockey Precast to develop additional storage space onsite. A road was regraded and the additional storage space enabled Shockey Precast to maintain its construction flow and finish precast erection four business days ahead of schedule. Excellent communication and collaboration among the Project Team helped Shockey Precast successfully deliver a great-looking building that also provides the Howard County Department of Fire & Rescue Services with a secure new home for its trucks. The Howard Hughes Merriweather Campus parking structure projects are examples of successful communication, collaboration, and problem-solving between Shockey Precast and the project team to achieve maximum value for the owner.

Project Details

Nine-level, 426,996-SF parking structure
1,307 pieces of precast
Two-crane, simultaneous construction
Erection completed ahead of schedule
Tight site with storage challenges

Architectural Details & Finishes

Three architectural concrete mixes
Panels cast in two colors
Framed spandrels
Columns combined to walls as pilasters

Do you have a similar project?

We’d love to hear more about it and answer any questions you have.

"Thank you for your professionalism and expertise on the Cornell University North Campus Residential Expansion. Your contributions were critical to our success."
Ben Robertson
Welliver
"Metromont was an excellent partner and worked seamlessly, closely to collaborate almost as an extension of our design team. It’s incredible how quickly it all came together.”
Scott Johnston
AIA Johnston Design Group
"The precast concrete design was able to meet the stringent performance requirements of the structure while providing an aesthetically pleasing, sustainable final product at an affordable price point."
Ben Townes
Townes + Architects
"Metromont’s team embraced our idea and got their whole team on board. It’s one thing for sales managers to want to make architects happy, but to have the plant manager, the finishing crew foreman and engineers fully engaged is something else. Metromont was extremely cooperative – the project was a win-win for everyone.”
K.J. Jacobs, AIA
McMillan Pazdan Smith

Let's Discuss Your Project

Our industry-leading experts are ready to answer your questions and put our proven experience to work for you. Contact us today and let’s discuss the ins and outs of your project.

Name(Required)
This field is for validation purposes and should be left unchanged.
Metromont Concrete Slab

Brightline Boca Raton Parking Garage

Boca Raton, FL

Miami-Dade County Health Department Parking Garage

Miami, FL

Whole Foods Market at Midtown Tampa

Tampa, FL

Spartanburg County Judicial Center Parking Deck

Spartanburg, SC

Tampa Heights Union Office Building & Parking Garage

Tampa, FL

PennFIRST Patient Pavilion Parking Structure

Philadelphia, PA

Liberty Place Parking Garage

Fredericksburg, VA

UNCW Central Parking Deck

Wilmington, NC

Seminole County Justice Annex & Parking Deck

Sanford, FL

UGA Hull Street Parking Deck Expansion

Athens, GA

2825 South, Sedgefield Mixed Use

Charlotte, NC

Cumming City Center Parking Deck

Cumming, GA

Wade V Parking Garage II

Raleigh, NC

City of Canton Parking Garage

Canton, GA

3800 Glenwood Parking Garage

Raleigh, NC

Palmer Lakes Logistics Center

Miami, FL

Bloc83 Parking Garage

Raleigh, NC

FirstHealth Parking Garage

Pinehurst, NC

Wilson Parking Garage

Wilson, NC

Fenton Parking Garage “D1”

Cary, NC

Parmer RTP Parking Garage II

Research Triangle Park, NC

Palisades III Office Building & Parking Garage

Raleigh, NC

The Grove at Towne Center

Snellville, GA

Science Museum of Virginia Parking Garage

Richmond, VA

Duke Health Green Level Parking Garage

Cary, NC

VCU Health Parking Garage

Richmond, VA

Gainesville North Parking Deck

Gainesville, GA

Confidential Company Headquarters

Naples, FL

Centene Headquarters North & South Parking Decks

Charlotte, NC

Lowe’s Global Technology Center

Charlotte, NC

The Beacon Parking Garage at Emory University Hospital Midtown

Atlanta, GA

10,000 Avalon

Alpharetta, GA

Alpharetta City Hall Parking Deck

Alpharetta, GA

Capitol Towers

Charlotte, NC

City of Buford Parking Garage

Buford, GA

CPCC Parking Deck

Charlotte, NC

Doral City Hall Office Building & Parking Garage

Doral, FL

Faraday Park West Parking Garage

Reston, VA

Heritage Plaza Office Building & Parking Garage

Lakeland, FL

Lenovo Campus Parking Deck

Morrisville, NC

LPL Financial

Fort Mill, SC

MUSC Bee Street Parking Deck

Charleston, SC

Peter J. Cannon Parking Deck

Columbia, SC

Pompano Beach Parking Garage

Pompano Beach, FL

Reynolds Street Parking Deck

Augusta, GA

River Pier Landing

Chattanooga, TN

South Falls Tower

Richmond, VA

The Brady Parking Deck

Atlanta, GA

The Standard at Atlanta

Atlanta, GA

Toyota of Murfreesboro

Murfreesboro, TN